Take a look at some of our successfully completed project for Reliance Industries Ltd, Jamnagar and Essar Project, Jamnagar.
Sr. No. | Description | Value(million) | Execution Year | Client |
---|---|---|---|---|
1 | Electrical Project work in Various plants in Refinery | 83.38 | 2007-13 | M/s RIL, Jamnagar |
2 | General Electrical work for Hydrogen, HMU, DM and OSBL area at Refinery | 57.24 | 2007-13 | M/s Essar Project (I), Limited, Jamnagar |
3 | Electrical Project work for 2x110 MW co-generation power plant (CPP) | 27.50 | 2009-13 | M/s Essar Project (I), Limited, Jamnagar |
4 | General Electrical works for 325MW Thermal power plant | 30.11 | 2011-13 | M/s Essar Project (I), Limited, Jamnagar |
5 | Electrical work to support Current Project a Various location in Refinery site (j3-Project) | 53.63 | 2013-15 | M/s RIL, Jamnagar |
6 | General Electrical work for Hydrogen, HMU, DM and OSBL area at Refinery | 1.97 | 2013-14 | M/s Essar Project (I), Limited, Jamnagar |